The US Navy is facing lengthy delays in extending the service life of its Tomahawk cruise missiles amid a shortage of the weapons. An analysis of budget documents by RIA Novosti revealed that deliveries of recertified missiles have been pushed back by more than a year, while orders have been sharply reduced.

Speaking at a Senate hearing on November 17, US Navy secretary nominee Hung Cao revealed that ammunition shortages had forced the American military to use expired Tomahawk missiles during its operation against Iran.

Tomahawk cruise missiles have a service life of 30 years, provided they undergo recertification after the first 15 years. The Navy initially planned to extend the operational life of 274 missiles under its fiscal year 2024 order. That figure was subsequently cut to 218, while initial deliveries were delayed by 15 months until August 2026, after the operation against Iran had already begun.

The fiscal year 2025 order suffered similar setbacks. The number of missiles scheduled for recertification was reduced from 252 to 164, with deliveries postponed from May 2026 to May 2027.

The latest budget report shows that the US Navy is not scheduled to receive a single recertified Tomahawk throughout the 2026 calendar year. Deliveries of the standard variant are expected to begin in May 2027, followed by the anti-ship version in September.

Processing times at Raytheon’s manufacturing facility have also increased dramatically. Recertification now takes 31 months instead of the previous 12, while the process for the anti-ship variant has stretched to 40 months.

The budget records, however, do not establish whether these delays affected the use of Tomahawk missiles during the US military operation against Iran.